Rollout of the National Broadband Plan
- Published on:
- Last updated on:
The main infrastructure build works for the rollout of the National Broadband Plan will be completed in counties across Ireland during 2026. This represents a major milestone in delivering universal high-speed broadband access across rural Ireland.
Completion Schedule:
| June 2026 |
| Kilkenny |
| Longford |
| July 2026 |
| Tipperary |
| Waterford |
| Meath |
| Westmeath |
| August 2026 |
| Dublin |
| September 2026 |
| Monaghan |
| Laois |
| Leitrim |
| Sligo |
| Offaly |
| Kildare |
| October 2026 |
| Roscommon |
| Louth |
| Wexford |
| Cavan |
| November 2026 |
| Clare |
| Wicklow |
| Donegal |
| Carlow |
| Kerry |
| December 2026 |
| Galway |
| Mayo |
| Cork |
| Limerick |