IWMG Commemorative Bridge project - June 2026 update
-
From: Office of Public Works
- Published on:
- Last updated on:
To whom it may concern,
Southside / Irish National War Memorial Gardens side. The reinstatement works for the pipeline diversion have now been completed with the site area being reduced. Embankment works and drainage works have been advanced. A temporary footpath on the riverbank has been reinstated for the regattas held in May. This will be closed again for a period when the bridge installation is ongoing.
On the northern side, on the Chapelizod Road, both north and south footpath service installation and finishes are now complete. DCC are currently awaiting ESB to provide connection. Resurfacing works for the service crossing are planned for late June. Preparation works are ongoing for the bridge delivery in August.