The Planning and Building Unit has kept under review the movements of Post-primary School building costs since the Basic Building Cost was increased to € 1,490/m2 in December 2018. As a result, it has been decided that the Cost Limits shown in Circular 0028/2021 will apply from 04 May 2021.

Sector: Post Primary

Author: Planning and Building Unit