IWMG Commemorative Bridge project - May 2026 update

Cuardaigh ar fad gov.ie

Bailiúcháin

IWMG Commemorative Bridge project - May 2026 update

IWMG Commemorative Bridge project - May 2026 update

To whom it may concern,

Southside / Irish National War Memorial Gardens side. The wingwalls are currently being backfilled and the back of wall drainage is being installed. The footpath along the riverbank on the southern side will remain temporarily closed to facilitate the reinstatement of the Gridline 70 (closest abutment to the river) and construction of the new footpath.

On the northern side, the roadworks on Chapelizod Road continue for the new pedestrian crossing. The new footpath at the southern side has been completed, works on the northern side started on the 5th May.

Foundations called wingwalls which will support a bridge over the river Liffey at the IWMG
Wingwalls for IWMG commemorative bridge

Is ann don fhoirm seo d’aiseolas, agus sin amháin, a bhaineann leis an leathanach reatha.

Ná cuir faisnéis phearsanta ná airgeadais san áireamh.

Chun gov.ie a fheabhsú, déanfar anailís ar an bhfaisnéis a chuireann tú isteach agus ní thabharfar freagra uirthi ar bhonn indibhidiúil.

Conas mar a bhí d’eispéireas ar an leathanach reatha? (ag teastáil)

Tá 400 carachtar fágtha agat