Proposed Commencement Schedule for Planning and Development Act of 2024
- Published on: 23 March 2026
- Last updated on: 23 March 2026
This page provides information on the remaining commencement phases of the Planning and Development Act 2024 (Act of 2024) i.e. provisions of that Act not yet in force and the “block” as part of which those provisions will be brought into force.
An asterisk (*) denotes a change as to what was proposed in the commencement schedule set out in the Implementation Plan as published March 2025. This is related to situations where a section or sections of a Part were brought into operation in an earlier block, or will be brought into operation in a later block, than originally proposed in that commencement schedule as published.
The following commencement schedule is subject to change as required.
Proposed Block C
Part 2 (Concept of Development)
- All remaining sections
Part 3 (Plans, Policies and Related Matters)
- Subsections (8) and (9) of section 25*
Part 4 (Development Consents)
- All remaining sections
Part 5 (Development at Dublin Airport)
- All sections
Part 6 (Environmental Assessments)
- All sections
Part 7 (Housing Strategy and Supply)
- Chapter 2 (Housing Supply)
Part 8 (Miscellaneous Powers of Planning Authorities)
- All sections
Part 10 (Architectural Heritage)
- All sections
Part 11 (Enforcement)
- All remaining sections
Part 12 (Appeal Procedures, Register, Records, etc.)
- All remaining sections
Part 15 (Compensation)
- All sections
Part 16 (Events and Funfairs)
- All remaining sections* (i.e. event licensing)
Part 18 (Office of the Planning Regulator)
- Section 550* (i.e. remaining section)
Part 19 (Further Provisions Relating to Planning Bodies)
- Sections 572 and 579 (i.e. remaining sections)
Part 20 (Financial and Miscellaneous Provisions)
- All remaining sections
Part 21 (Strategic Development Zones)
- All sections*
Part 22 (Urban Development Zones)
- All remaining sections*
Part 23 (Additional Transitional and Related Provisions)
- All remaining sections
Part 24 (Consequential amendments)
- As required
Proposed Block D
Part 9 (Judicial Review)
- Chapter 2 (Costs relating to certain proceedings)
Part 13 (Appropriation, Disposal, Development of Land)
- All sections
Part 14 (Compulsory Acquisition and Purchase of Land)
- All sections
Part 17 (An Coimisiún Pleanála)
- All remaining sections* (i.e. sections 532 and 533)
Part 24 (Consequential amendments)
- All remaining sections