November 2025 Update – Dublin Commemorative Bridge
-
From: Office of Public Works
- Published on: 10 November 2025
- Last updated on: 10 November 2025
Works are continuing at the southern pier and abutment on the Irish National War Memorial Gardens side. Current activities include archaeological monitoring, installation of silt fences, topsoil stripping, site investigations, and installation of continuous flight auger (CFA) piles. Upcoming works on the southern side will involve diverting the foul sewer pipeline, completing the bridge foundation test pile, and commencing the bridge concrete works.
On the northern side, works are progressing with the construction of the piling platform for the bridge foundations. Future activities will include the installation of CFA piles, further site investigations, completion of test piles, and off-site removal of arisings.